Scope: Cleaning of various process vessels including IP Separator, Electrostatic Treater, Crude Degasser, LP Separator, and Produced Water Degasser.System Used: 2 units of SV60V.Manpower: 11 personnel.Duration: 13 days …
Scope: Cleaning of various process vessels including IP Separator, Electrostatic Treater, Crude Degasser, LP Separator, and Produced Water Degasser.System Used: 2 units of SV60V.Manpower: 11 personnel.Duration: 13 days – 4 days of preparation, 7 days of desanding/cleaning, and 2 days of housekeeping.Result: Full cleaning of topside process vessels with reduced downtime and enhanced safety.